City of Prescott
Chino Production Well 4 Rehabilitation


Scope of work
Chino Production Well 4 was evaluated from the well casing throughout and was equipped with all new pumps, piping, electrical, electrical controls, building, perimeter walls, fencing, retention basins, and access roads. Well 4 is the latest to be completed as part of a program to develop a standardized well site design template that can be customized to work for all City of Prescott well sites. Fann Environmental worked closely with Dibble Engineering for this Design-Build project. Three additional wells will be similarly rehabilitated as part of the program.
Project details
Owner: City of Prescott
Delivery Method: Design-Build
Contract Value: $5,000,000 total combined estimated GMP
Year Completed: 2020