This Arizona Water Company Design-Build project is located in the Heber-Overgaard area of Arizona. As a Design-Build project we partnered with Waterworks Engineers for the engineering and design portion of this project. We installed a new Arsenic Treatment Facility complete with a new building using AdEdge E33 Adsorption Technology technology arsenic treatment equipment including a backwash recycling system. We also re-equipped the well with a new pump, motor and a Lakos downhole sand separator.

Project details

Owner: Arizona Water Company
Delivery Method: Design-Build
Contract Value: $708,000
Year Completed:   2018