Town of Chino Valley
Wastewater Treatment Facility


Scope of work
This project was developed as a unique public/private partnership. Fann Contracting financed and constructed this 1.0 mgd facility. This Construction Manager at Risk project was completed by the Fann Environmental team with design by Aqua Engineering, Inc and included the construction of a one million gallon per day Enviroquip/Kubota MBR treatment plant, lift station, effluent booster facility, and gravity main.
The Fann Environmental team began work on this project at the 60% design phase. The work included scheduling, constructability reviews, and value engineering during preconstruction. The FE team visited MBR treatment plants and assisted the design engineer with equipment selction. It also developed cost saving changes to the headworks and piping schemes.
Fann Environmental provided 10 years of operational and maintenance services to Fann Contracting, Inc for this facility.
The Fann Environmental team began work on this project at the 60% design phase. The work included scheduling, constructability reviews, and value engineering during preconstruction. The FE team visited MBR treatment plants and assisted the design engineer with equipment selction. It also developed cost saving changes to the headworks and piping schemes.
Fann Environmental provided 10 years of operational and maintenance services to Fann Contracting, Inc for this facility.
Project details
Owner: Town of Chino Valley
Delivery Method: Construction Manager at Risk
Role:
Contract Value: $13,000,000
Year Completed: 2004
Delivery Method: Construction Manager at Risk
Role:
Contract Value: $13,000,000
Year Completed: 2004